SAMPLE
CRITICAL ITEMS SUMMARY
ITEM
DESCRIPTION
SPEC
DRAWING
1.
Geotechnical Engineer:  Ensure a qualified
01450
7066058
Geotechnical Engineer observes the pile
Para 1.3.1
driving operations and is available to
answer questions that arise.
2.
Piles:
a.
Ensure a qualified/experienced person
02456
maintains the pile driving records
Para 3.2.2
which includes the blow counts.
b.
Check the Contractor's pile driver,
02456
7066058
equipment, method of positioning
Para 3.1.3
piles and proposed pile driving
" 3.2.2
schedule.
c.
Do not overdrive piles since they
02456
7066061
are friction piles.  If the Contractor
Para 3.1.8
should accidentally overdrive a pile,
be sure to get the pile driving history
of that pile and have the Contractor
design the required buildup section in
accordance with the specs and forward
to the designers by courier as soon as
possible, advising the designers by
telephone or cable that the information
is on its way.
3.
Underwharf Vaults:  The underwharf vaults
03300
7066061
are precast.  Be sure that the Contractor
Para 3.3.3
provides shop drawings for the precast
07170
7066059
vault.  The shop drawings should show
Para 3.1
the lifting points and the lifting system.
Have the designers check the Contractor's
approved shop drawings.  Be sure the vaults
are waterproofed inside and out and that
they are in the proper place before the pile
caps and deck are cast-in-place.