Custom Search
 
  
 


PERFORMANCE REQUIREMENTS
CONTRACT REQUIREMENTS
(5)
(6)
(4)
(3)
(2)
(1)
WGT
STANDARD OF
MADR
WORK
CONTRACT
ITEM
PERFORMANCE
REQUIREMENT
(%)
REQUIREMENT
NO
15
2%
Attachment J-C2, Contrac-
a. Completed during specified
Tree Pruning
007
tor's approved schedule
periods and as scheduled
(Paragraph C.9)
2%
70
Tree balanced and formed,
b. Properly pruned
dead/diseased/dangerous &
obstructed wood removed;
sprouts removed,
no remaining branch
branch stubs
(Paragraph C.9.g)
2%
15
Debris and pruned vegeta-
c. Debris/vegetation removed
tion removed from site
same day
(Paragraph C.9.g)
15
3%
Attachment J-C2, Contrac-
a. Completed during specified
Hedge Trimming
008
tor's approved schedule
periods and as scheduled
(Paragraph C.9)
70
3%
Plant balanced and formed,
b. Properly trimmed
extraneous dead/diseased &
new growth removed, area
reduced, doors, windows,
walks clear
(Paragraph C.9.h)
15
c. Debris/vegetation removed
Debris and trimmed vegeta-
3%
tion removed from site
same day
(Paragraph C.9.h)








Western Governors University
 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business