Share on Google+Share on FacebookShare on LinkedInShare on TwitterShare on DiggShare on Stumble Upon
Custom Search
 
  
 


Contact should be made with the PM prior to the pre -final submission to reconfirm
programmed construction costs for the contract. Where A&E estimate exceeds programmed
construction costs, recommendations for cost reduction or proposed bid items must be
provided with the pre -final submission.
7.2.3 FINAL
The final estimate submittals shall include the complete estimate on CD -R, the same as
the pre-final except for correction/inclusion of pre -final comments.
79








Western Governors University
 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business