protection levels are per National Association of Corros ion Engineers (NACE) recommended
practices.
d. Confirmation of interference current mitigation to other structures.
e. Provide ROICC with "punch list" of construction contractor deficiencies on the
installation of the cathodic protection systems.
f. Prepare a final inspection report noting all test results to document levels of cathodic
protection throughout the structure and to establish baseline parameters.