c. Basis of Design, including Design Calculations
d. Cost Estimates
e. Soils Investigation Report
f. Annotated Review Comments of the previous submittal
g. All marked review copies of the previous submittal
h. List of Required Contractor Submittals
i. Designer to ROICC Report
j. Annotated Review Requirements Checklist
3.1.4.1 List of Required Contractor Submittals. The A-E shall provide a list of the shop
drawings, catalog cuts, samples and other items that are required by the Specifications to be
submitted by the construction contractor. In addition, the A-E shall indicate the submittals that
are to be reviewed by the Government and the submittals that are to be reviewed by the A-E.
As a minimum, the A-E shall review all submittals requiring technical review.
3.1.4.2 Designer to ROICC Report.  In the report, the A-E shall provide: 1) an overall
description of the project; 2) a general overview of the construction sequence that was intended,
and, in particular, any step(s) or technique(s) critical to the successful completion of the project;
3) any particular aspect of the construction sequence that requires extra attention or inspection
by the ROICC; 4) a list of construction items for which field consultation by the A-E is
recommended.
3.1.5 Final Submittal. The Final Submittal shall include the originals and the specified
number of copies of the following as specified in the "Scope."
a. Working Drawings
b. Specifications
c. Cost Estimates
d. Basis of Design, including Design Calculations
e. Soils Investigation Report
f. Field Notes (including survey field books)
g. Review Requirements Checklist
3-3