Share on Google+Share on FacebookShare on LinkedInShare on TwitterShare on DiggShare on Stumble Upon
Custom Search
 
  
 


REVIEWERS
INITIALS AT:
CIVIL (Cont'd)
100%
35%
Pavements:
3.
a.
Adequate soil exploration and soil
tests were performed...............
b.
Type and volume of traffic,
controlling wheel loads and
configurations were considered.....
c.
Adequate drainage is provided.......
d.
Cut and fill is balanced and not
excessive...........................
e.
Construction materials and debris
disposal site(s) are available nearby.
f.
Adequate/required clearances are
provided . . . . . . . . . . . . . . . . . . . . . . . . . .
g.
Material selection is in compliance
with directives..................
h.
Ground water table/high water/frost
line was considered.................
i.
Expansion capability provided if
required . . . . . . . . . . . . . . . . . . .
j.
Navigational  aids/markings/signs
provided where required.............
k.
Erosion controls are provided.......
l.
Interium  traffic  routing/controls/haul
road maintenance and repairs considered
Adequate surveys, cross sections/profile
m.
controls are provided...............
Proper Joint details clearly shown.
n.
4.
Adequate Topographic and Hydrographic
survey data is provided.............
5.
Existing utility lines, fences,
underground utilities and other
obstructions to new construction is
clearly shown on drawing...............
2








Western Governors University
 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business