4. ESTABLISHMENT AND APPROVAL OF VE TEAM VE services shall be
performed by a second team Of designers, separate and completely
independent from the original designers which prepare the 35%
plans and specifications. The VE services shall be directed by a
qualified firm or persons having Certified Value Specialist (CVS)
credentials that qualify them to perform such services.
5. LEVEL OF EFFORT.
Typically Design A/E Effort:
PM
ARCH
STRUCT
ME
EE
CE
------------------------------------
2
4
4
4
4
8
Coordinate/discuss project
8
8
0
8
8
8
Review/comment
Resolution of Proposals -- part of 35% Review Board
Meeting--
Submit Final Report
8
-----------------------------
12
12
12
12
12
24
84 hours total
6 . P- - -J-E-C T -D A- - - - - - -B E - F U- - -I- -H E D .
RO
- - - - TA TO - - - - RN S -
Prior to commencing a VE study, the design A/E will forward
the following information to the VE Team.
(1)
Two sets of 35% drawings (full site)
(2)
Specifications - 2 copies
(3)
Detailed Cost Estimates - 4 copies
(4)
Design Analysis (Basis of design; calculations) - 4
copies
(5)
Economic Analysis of Design Alternatives Report
Boring logs and soil reports
(6)
* (7)
Computer Energy/System Analysis and Energy Conservation
Report
*If required by Appendix "A"
7.
CERTIFIED VALUE SPECIALISTS (CVS) RESPONSIBILITIES.
--------------------------------------------------
Pre Study
a.
(1)
Review complete design package and identify high
cost areas.
Prepare cost model (actual vs. historical).
(2)
Prepare bar graphs of all sub systems.
(3)
Prepare preliminary cost worth ratios.
(4)
40 Hour Study
b.
(1)
Team leader avid coordinator
(2)
Team recorder
2
Attachment 22A
2 of 5
|
||