Table 1-2
UNDERWATER (U/W) INSPECTION REPORT OUTLINE
Report Cover (Government Furnished)
Title Page
Executive Summary (light blue paper)
Executive Summary Table (light blue paper)
Table of Contents
List of Figures
List of Photographs
Introduction
Section 1.
Project Task Description
1.1
Report Content
1.2
etc.
1.3
Activity Description (Information that will effect
Section 2.
i n s p e c t i o n , repair, or rate of deterioration taken from
Base Station Master Plan)
Activity Location
2.1
Existing Waterfront Facilities at Activity
2.2
Climate
2.3
Topography, Hydrology, Oceanographic Date
2.4
etc.
2.5
Inspection Procedure
Section 3.
Level(s) of Effort
3.1
Inspection  Pattern/Procedure
3.2
Equipment
3.3
etc.
3.4
Facilities Inspected
Section 4.
Type Facility and Number
4.1
Description
4.1.1
Observed Inspected Condition
4.1.2
Structural Condition Assessment
4.1.3
Recommendations
4.1.4
Conclusions
4.1.5
Repeat as Necessary
4.2
Appendices
Field Notes
A
Backup Data for Cost Estimates (gross)
B
Backup Computations of Structural Analysis (sample)
C
Measured Data (thickness measurements, etc.)
D
Bibliography or any References
E
17








Western Governors University
 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business