Custom Search
 
  
 


4
GLAZING
PAGE
EXPLANATION AND SCOPE OF STANDARDS
Application
These standards apply to installing glass in doors or windows that are
within reach when standing.  Task time standards for surface preparation
and ladder use must be added as required.
Remarks
The removal and installation of framed window screens has been developed
as a separate standard.  This standard is added when it is necessary to
remove a screen to gain access to a pane that needs work.
Materials
Hand tools, glass, spacer shims, glazer points, glazing compound, putty,
caulking compound and sealants.
6. JOB PHASE DESCRIPTION
Replace twenty (20) panes of 24" X 24" glass in wood sashes.
Removal of screens and cutting of glass are required.
9. EPS ESTIMATED TIME
NON-EPS
UNIT
CRAFT
OCCUR-
REFERENCE
ESTIMATED
TASK DESCRIPTION
HOURS
TIME
RENCE
TIME
7
6
a.
b.
10
C.
PT-231
Remove and i n s t a l l (20) screens
.0488
20
1.0
20
9.4
PT-213
Remove and install (20) panes of 24" X 24" glass .0466
in wood sashes when cutting of glass is required
NOTE:
Add ladder use if appropriate to complete
craft time.
4