PT-121
PT-126
BRUSH ONE COAT OF PAINT ON DOOR PANEL(S) OR
BRUSH ONE COAT OF PAINT ON 1/2" DIA TO 1-1/2" DIA
SIDE(S)
PIPE
NO WORK UNIT DESCRIPTION
NO WORK UNIT DESCRIPTION
====================================================
====================================================
1 APPLY A COAT OF PAINT ON DOOR PANEL(S) OR SIDE(S)
1 APPLY ONE COAT OF PAINT ON 1/2" TO 1-1/2" DIA PIPE
WITH BRUSH
WITH BRUSH
2 IN-PROCESS SET UP AND HANDLING TIME
2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING
3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING
PT-126 =
.00596 HRS PER LIN FT
PT-121 =
.00486 HRS PER SQ FT
PT-127
PT-122
BRUSH ONE COAT OF PAINT ON OVER 1-1/2" DIA TO 4"
BRUSH ONE COAT OF PAINT ON DOOR EDGES
DIA PIPE
NO WORK UNIT DESCRIPTION
NO WORK UNIT DESCRIPTION
==================================================== -
----
====================================================
1 APPLY ONE COAT OF PAINT ON DOOR EDGES WITH BRUSH
1 APPLY ONE COAT OF PAINT ON OVER 1-1/2" DIA TO 4"
2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING
OR COLUMN WITH BRUSH
2 ADDITIONAL JOB PREPARATION TINE FOR PAINTING
PT-122 =
.00403 HRS PER LIN FT
PT-127 =
.01083 HRS PER LIN FT
PT-123
PT-128
BRUSH COAT OF PAINT ON DOORWAY OR DOOR JAMB AND
BRUSH ONE COAT OF PAINT ON OVER 4" DIA TO 8" DIA
CASING
PIPE OR COLUMN
NO WORK UNIT DESCRIPTION
====================================================
NO WORK UNIT DESCRIPTION
====================================================
1 APPLY ONE COAT OF PRIMER OR PAINT ON DOOR JAMB OR
CASING WITH BRUSH
1 APPLY ONE COAT OF PAINT ON OVER 4" DIA TO 8" DIA
2 IN-PROCESS SET UP AND HANDLING TIME
PIPE WITH BRUSH
3 ADDITIONAL Jo8 PREPARATION TIME FOR PAINTING
2 ADDITIONAL JO8 PREPARATION TIME FOR PAINTING
.02017 HRS PER LIN FT
PT-123 =
.00548 HRS PER LIN FT
PT-128 =
PT-124
PT-129
BRUSH COAT OF PAINT ON EXPOSED RAFTERS (16"-20"
BRUSH FINISH COAT OF PAINT ON METAL GRILLE
-24" C.C.), ALSO INCLUDES TWO SIDES AND EDGE OF
FASCIA, EAVE SECTION (UNDERSIDE OF SHEATHING BE-
NO WORK UNIT DESCRIPTION
====================================================
TWEEN RAFTERS), AND EDGE AND SIDE OF EAVE BLOCKS
(PER LIN FT OF ROOF)
1 APPLY OWE COAT OF PAINT ON METAL GRILLE USING 5"
BRUSH
2 IN-PROCESS SETUP AND HANDLING TIME
NO WORK UNIT DESCRIPTION
====================================================
3 ADDITION JOB PREPARATION TIME FOR PAINTING
1 APPLY COAT OF PAINT ON FASCIA, 2 SIDES AND 1 EDGE
.01344 HRS PER SQ FT
PT-124 =
2 APPLY COAT OF PAINT ON RAFTERS, 2 SIDES AND 1 EDGE
3 APPLY COAT OF PAINT ON EAVE SECTION
4 APPLY COAT OF PAINT ON EAVE BLOCKS, 2 SURFACES
5 ADDITIONAL JOB PREPARATION TIME FOR PAINTING
PT-125
.04976 HRS PER LIN FT
PT-129 =
BRUSH ONE COAT OF PAINT ON 4" GUTTER
NO WORK UNIT DESCRIPTION
====================================================
1 APPLY ONE COAT OF PAINT ON 4" GUTTER USING BRUSH
2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING
.01956 HRS PER LIN FT
PT-125 =
22