PT-412
PT-330
AIRLESS SPRAY PAINTING REQUIRING EXTRA CARE FOR A
ROLLER PAINT WALLS OF A ROOM WITH 8' TO 10' HIGH
QUALITY FINISH
CEILING, (INCLUDES "CUTTING IN" CORNERS, BASEBOARD,
CEILING, AROUND DOOR(S) AND WINDOWS WITH BRUSH)
NO WORK UNIT DESCRIPTION
(PER SQ FT OF WALL BEING PAINTED)
====================================================
1 AIRLESS SPRAY PAINTING REQUIRING EXTRA CARE
NO WORK UNIT DESCRIPTION
====================================================
2 ADDITIONAL JOB PREPARATIW TIME FOR PAINTING
1 "CUT IN" CORNERS IN A ROOM USING BRUSH
PT-412 =
.00177 HRS PER SQ FT
2 "CUT-IN" BASEBOARD AND CEILING IN A ROOM USING BRUSH
3 "CUT IN" AROUND DOOR(S) AND WINDOWS USING BRUSH
4 APPLY PAINT TO WALLS USING ROLLER
PT-415
5 ADDITIONAL JOB PREPARATION FOR PAINTING
AIRLESS SPRAY PAINTING OF IRREGULAR SURFACE
.00352 HRS PER SQ FT
PT-330 =
NO WORK UNIT DESCRIPTION
====================================================
1 AIRLESS SPRAY PAINTING OF IRREGULAR SURFACE
PT-340
2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING
ROLLER PAINT WALLS AND CEILING OF A ROOM WITH 8'
PT-415 =
.00209 HRS PER SQ FT
TO 10' HIGH CEILING, (INCLUDES "CUTTING IN" COR-
NERS, BASEBOARD, AROUND DOOR(S) AND WINDOWS WITH
BRUSH
(PER SQ FT OF LULL BEING PAINTED)
PT-417
NO WORK UNIT DESCRIPTION
====================================================
AIRLESS SPRAY PAINTING OF STRUCTURAL MEMBERS
1 "CUT IN" CORNERS IN A ROOM USING BRUSH
NO WORK UNIT DESCRIPTION
2 "CUT IN" BASEBOARD IN ROOM USING BRUSH
====================================================
3 "CUT IN" AROUND DOOR(S) AND WINDOWS USING BRUSH
1 AIRLESS SPRAY PAINTING OF STRUCTURAL MEMBERS
4 APPLY PAINT TO WALLS USING A ROLLER
2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING
5 APPLY PAINT TO CEILING USING A ROLLER
6 ADDITIONAL JOB PREPARATION FOR PAINTING
PT-417 =
.00173 HRS PER SQ FT
PT-340 =
.00420 HRS PER SQ FT
PT-421
PT-350
CONVENTIONAL SPRAY PAINTING OF FLAT SURFACE
APPLY ONE COAT OF PAINT TO BOTH SIDES OF A CHAIN
NO WORK UNIT DESCRIPTION
LINK FENCE WITH ROLLER
====================================================
1 SPRAY ONE COAT ON FLAT SURFACE
NO WORK UNIT DESCRIPTION
====================================================
2 ADDITIONAL JOB PREPARATION TIRE FOR PAINTING
1 ROLL PAINT BOTH SIDES OF CHAIN LINK FENCE
.00160 HRS PER SQ FT
PT-421 =
2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING
PT-350 =
.00363 HRS PER SQ FT
PT-422
CONVENTIONAL SPRAY PAINTING REQUIRING EXTRA CARE
PT-411
FOR A QUALITY FINISH
AIRLESS SPRAY PAINTING OF FLAT SURFACE
NO WORK UNIT DESCRIPTION
====================================================
NO WORK UNIT DESCRIPTION
====================================================
1 CONVENTIONAL SPRAY ON SURFACE REQUIRING EXTRA CARE
2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING
1 AIRLESS SPRAY PAINTING OF FLAT SURFACE
2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING
PT-422 =
.00253 HRS PER SQ FT
PT-411 =
.00111 HRS PER SQ FT