M.3
FAR 52.217-5, EVALUATION OF OPTIONS (JUL 1990)
***********************************************************************
NOTE: If this provision is not appropriate, insert the "EVALUATION
EXCLUSIVE OF OPTIONS (FAR 52.217-3) provision.
***********************************************************************
a. Except when it is determined in accordance with FAR 17.206(b) not
to be in the Government's best interests, the Government will evaluate
offers for award purposes by adding the total price for all options to the
total price for the basic requirement. Evaluation of options will not
obligate the Government to exercise the option(s).
M.4
FAR 52.232-15, PROGRESS PAYMENTS NOT INCLUDED (APR 1984)
A progress payments clause is not included in this solicitation, and will
not be added to the resulting contract at the time of award. Bids
conditioned upon inclusion of a progress payment clause in the resulting
contract will be rejected as nonresponsive.