Custom Search
|
|
|
||
MIL-HDBK-1013/12
4.8.1
Required Information. The following information is
required for the evaluation reconciliation procedure:
a) Worksheets (see Appendix B):
1) Cross-Section Evaluation (CSE)
2) Frame Evaluation (FE)
3) Anchorage Evaluation (AE)
4) Wall Evaluation (WE)
4.9
Requirements Revision Procedure. This procedure
provides structures to revise requirements for protecting a
facility against ballistic, bomb, and forced entry attacks.
Figure 14 shows the process chart for the requirements revision
procedure. Figure 15 explains the structures contained in Figure
14.
4.9.1
Required Information. The following information is
required for the requirements revision procedure:
a)
Security procedures
b)
Justification for window
c)
Site layout
d)
Worksheets (see Appendix B):
1)None
42
|
||