Tweet |
Custom Search
|
|
|
||
MIL-HDBK-1038
h) Are there any other conditions or operational requirements that should
be considered in the design and fabrication of the crane(s)?
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________
Provide sketches and complete description for all of the above features
that apply. Add any other features or requirements that may be appropriate.
16.
INSTRUCTIONS FOR CLEARANCE SKETCH AND FLOOR PLAN:
a) The "C" dimension is measured from the top of the rail to the lowest
overhead obstruction (bottom chord of truss, light fixtures, beams, knee braces,
ducts, pipes, conduits, etc.)
b) Loads "K" and "P" are the wheel loads (without impact), and
dimensions "L", "M", "N", and "Q" are the spacings that were used for the design
of the runway girders.
c) If the particular runway girder is of a different construction than
shown on the clearance sketch, provide a new sketch showing the appropriate
details of the girder.
d)
Show the cardinal compass directions.
e) Show the required load hook approaches, of both hoists, at each end
of runway and ends of the crane bridge.
f)
Show access platform(s) to the crane.
g)
Show runway girder support columns and spacing.
224
|
||