4/17/93
D. DISTRIBUTION: Same as 35% Submittal.
3.3.3
35% SUBMITTAL
A. PURPOSE: This submittal allows the activity to review and concur with
the A&E's interpretation of the functional and organizational requirements of the
project. Concurrently, LANTNAVFACENGCOM is reviewing to assure technical
features comply with the Department of Defense and Navy policies and regulations.
This submittal is intended to clarify and establish specific requirements for the project.
If a 35% submittal is required, no PEP submittal is required.
B. ELEMENTS:
(1) Drawings - Include as a minimum the following:
(a) Civil
Site Plan
Utility Plan
(b) Architectural
Floor Plans - Including room names and dimensions
Furniture Footprint Plan - Reflecting and including an updated
collateral equipment list coordinated with the activity.
Finish Schedule
Roof Plan
Elevations
Typical Wall Section
(c) Structural
Foundation Plan
Floor Framing Plan
Roof Framing Plan
3-7