h. Identify the short circuit currents for all protective devices and switchgear. Select
and indicate the set points and operating ranges of all protection devices to ensure
that the electrical system is properly coordinated.
5.9 ENVIRONMENTAL
The A-E shall comply with the regulations promulgated by the Department of Defense Overseas
Environmental Baseline Guidance Document (OEBGD) of October 1992.
5.9.1 Environmental Considerations. Explain the measures proposed for the preservation of
trees, plants, wildlife, air and water; for pollution abatement; and for the blending of the project
with the surroundings.
Thoroughly investigate and adhere to the provisions of the OEBGD; or to local government laws
and regulations whenever the OEBGD does not provide a regulation, standard' or governing
criteria.  Fully describe all sensitive environmental issues which are (or may become)
controversial.
The OEBGD provides guidance regarding the following:
Air Emissions
Drinking Water
Wastewater
Hazardous Materials
Hazardous Waste
Solid Waste
Medical Waste Management
Petroleum Oil Lubricants (POL)
Noise
Pesticides
Historic & Cultural Resources
Natural Resources and Endangered Species
Polychlorinated Biphenyls
Asbestos
Radon
Spill Prevention & Response Planning
Underground Storage Tanks
5.9.2 During Construction. Explain the measures included in the specification to minimize
the temporary disruption of the environment during construction. Include a discussion of the
following.
a. Noise from equipment and construction.
b. Dust from the construction site, access roads, sandblasting operations, and or
masonry work.