PACNAVFACENCOMINST 4335.2
20 FEB 1992
ARCHITECT-ENGINEER FINANCIAL RESPONSIBILITY, FINDINGS AND RECOMMENDATION
Subj:
3. When action to recover is recommended, provide cost data (i.e., copies of
memorandum of negotiation or business clearance for the construction contract
modification resulting from the A-E liability) and, if appropriate, comments
regarding the reasonableness of this cost data. If construction contract
modification is not yet negotiated, provide estimate of the recoverable damage.
Technical Adviser
Legal Advisor
Contracting Officer
Comments/Action:
Approved/Denied
Date
Contracting Officer
copy to:
PACNAVFACENGCOM (Codes 09C, 02, 04, 05)
A-E Liability Coordinator
Design Contract File (after approval by Contracting Officer)
Construction Contract File (after approval by Contracting Officer)
|
||