REVIEWERS
INITIALS AT:
SPECIFICATIONS
100%
35%
1.
Refer to sheet index to verify that all
sheets are included . . . . . . . . . . . . . . . . . . . . .
2. Project specifications are free of trade
name, proprietary and restrictive
requirements . . . . . . . . . . . . . . . . . . . .
3.
Terminology used in specifications and
drawings are the same. . . . . . . . . . . .
References to drawings in specifications
4.
are clearly shown on the drawings.......
5.
Title of project specification is
identical with that shown on the drawings.
6.
Technical sections of project
specifications have been edited and
tailored to fit the project in accordance
with requirements of PACNAVFAC P-6,
especially when type specifications (TS)
are utilized . . . . . . . . . . . . . . . . . . . . . . . . . . . .
7.
Construction category codes are correct,
properly listed, and complete . . . . . . . . . . .
8.
All interior and exterior finishes are
identified . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9.
Applicable environmental protection
requirements are incorporated...........
10.
Time for completion of project is
adequate (Long lead items are considered).
11.
Liquidated damages established per
NAVFAC P-68 . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
12.
Types, classes, styles, and similar
requirements of referenced
specifications are specified............
Special operational safety and administrative
13.
requirements having an effect on sequence
of operation, scheduling and completion
time are specified . . . . . . . . . . . . . . . . . . . . . .
14.
Bid items, additive/deductive, and
combinations thereof were considered with
no more than three additive bid items...