The following are blank forms to be used for the preparation of construction
cost estimates and which have been referenced in the preceding text:
Cost Estimate Backup Sheets
-
Attached.  Two versions available
(NAVFAC Form 11013/7 1-78)
computerized ("detailed" and "system"
costs).
Markup Summary Sheets (3 pgs) -
Attached.
Available computerized.
Building Budget Estimate
-
Attached.
Available computerized.
Summary Sheet (2 pgs)
Cost Analysis Sheet (2 pgs)
-
Attached.
Available computerized.
Cost Tracking Sheet (2 pgs)
-
Attached.
Available computerized.
CQC Requirements Form (3 pgs) -
Attached.
Checklist of Overhead Cost
-
Attached.
Available computerized.
Items (3 pgs)
Cost Estimate Completion
-
Attached.
Checklist (6 pgs)
Air Force Form 1178 (3 pgs)
-
Attached.
NAVFAC Form 4330/43 (2 pgs)
-
Attached.
ADDITIONAL INFORMATION
The following information in MIL-HDBK-1010 is pertinent and necessary to the
preparation of A/E prepared construction cost estimates:
CES Standard Systems List
-
Pages 160-164 - Lists standard systems for
building and supporting facilities and
identifies built-in equipment items with a
"(1)".
CES Standard Systems
-
Pages 252 to 280 - Describes line items
Narratives
associated with each system.
Building Budget Estimate
-
Pages 93 to 94 - Instructions for
Summary Sheet
preparation.
NAVFAC Construction Cost
-
Attached to MIL-HDBK 1010.
Index (Escalation Rates)
Area Cost Factors (ACFs)
-
Attached to MIL-HDBK 1010 - Fill in at
appropriate location on Building Budget
Estimate Summary Sheet.