Submittal Requirements.
5.
a. Concept Submittal (6 copies required) - The purpose of this
submittal is to present, for approval, an overall plan to be followed during
the ongoing preparation of the manual. This submittal will include but not
be limited to providing the following information:
(1) Identify by name all systems that will be addressed in the
manual.
(2) Provide the format of the manual and include the following:
(a) Sample three-ring loose-leaf binder. Show a typical. title
as it will appear on the front face and also on the ring end of the binder.
(b) Provide a sample divider.
(c) Provide samples showing the quality of paper and the
quality of reproduction proposed.
(d) Select one representative system of moderate complexity
and partially develop the various operations and maintenance aspects of the
system. This development should have sufficient depth to clearly
demonstrate the arrangement and level of detail proposed for all systems
t h a t will be included,
(e) Other documents which, in the A/E's judgment, should be
submitted for approval.
Submittal Schedule.
6.
a. The submittal date shown is the day the item is due at the office
o f the contracting officer.
*(1) Concepts submittal - within 30 calendar days after award of
o p t i o n . (1 copy)
* ( 2 ) Prefinal submittal - 30 calendar days prior to DOD/Acceptance.
( 3 copies)
* ( 3 ) Final submittal - 90 calendar days after BOD/Acceptance.
( 3 copies)
b .  Submittal schedule, work and services shall be completed to assure
economical, safe, life cycle operation and maintenance of the facility by
the Government.
*NOTE: Option under Post Construction Award Services (PCAS)
-2-
Attachment 23A
2 of 7








Western Governors University
 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business