Jun 95 (Rev. 9/99)
LIQUIDATED DAMAGES
(From NAVFAC P-68, Contracting Manual, Mar 94)
******************************************************************************
TABLE 1: GENERAL CONSTRUCTION PROJECTS
Estimated Liquidated Damages
Project Cost
Per Calendar Day
______________________________________________________________________________
2,000-25,000
$ 80
25,000-50,000
110
50,000-100,000
140
100,000-500,000
200
Each Additional $100,000 add $50
******************************************************************************
TABLE 2: FAMILY HOUSING UNITS
Liquidated Damages
Type of Units
Calendar Day Per Unit
______________________________________________________________________________
GOQ (General Officers' Qtrs)
Average daily Basic Allowance for
SOQ (Senior Officers' Qtrs)
Housing (BAH) with dependents plus
FGO (Field Grade Officers)
average applicable housing
CGO (Company Grade Officers)
allowances or temporary living
SEM (Senior Enlisted Men)
allowance, as appropriate.
JEM (Junior Enlisted Men)
******************************************************************************
TABLE 3: BACHELOR HOUSING
Type of
Rate Per
No. of Men
Liquidated Damages
Housing
Calendar Day
Per Bldg.
Calendar Day per Bldg.
______________________________________________________________________________
BOQ BAQ Rate for single
x _____
= _____
03 rate plus single
03 rate for Basic
Allowance for Housing
(BAH) for area.
BEQ BAQ Rate for E-5 plus
single E-5 rate for
Basic Allowance for
Housing (BAH) for
area.
For Hawaii projects: Call Personnel Support Activity Detachment (PSD),
Financial Section, at (808) 471-2405, extension 316, for current liquidated
damages rates in Table 2, FAMILY HOUSING UNITS and Table 3, BACHELOR HOUSING.
PSD will provide Basic Allowance for Housing (BAH) monthly rates, which must
be divided by 30 (days) for a daily rate of liquidated damages.