I. PACNAVFACENGCOM DESIGN REVIEW CHECKLIST
Project Title:__________________________________________________________________
______________________________________________________________________________
Reviewer's
60% _________________________________
Date: __________________
Signature:
100% _________________________________
Date: __________________
Review Item
Yes * No
N/A
Cost Engineering
1.
Signed statement certifying final estimate is based on final drawings
and specifications provided.
2.
Quotes from suppliers and manufacturers, with name, telephone
number, and date, for items greater than 10% of the construction cost
estimates provided.
3.
Narrative on the factors and sources of cost data used in developing
the estimate provided.
4.
Bid item costs identified separately.
*Note: Provide explanation for "No" responses.
APPENDIX I