ITEM
DESCRIPTION
SPEC
DRAWING
4.
Electrical:
a.
Where new lines cross or follow an
7066036
existing line be sure that outages
7066037
on the existing lines are coordinated
7066038
so that the Contractor does not have
to work the lines hot. Determine if
outages will be required during other
than working hours due to station loads
and that proper safety precautions,
such as the use of blankets, are taken.
b.
The switchgear, transformer and the
16360
7066065
600 MCM cable are long lead time items.
16361
7066069
Although 600 MCM is a standard size
cable, it is not a cable that is
normally kept in stock by the cable
manufacturers. The switchgear,
transformer, and the 600 MCM cable will
have to be manufactured after the
Contractor places his order. Thus,
every effort should be made to get the
Contractor to turn in his shop drawings
and catalog cuts as soon as possible.
c.
Splices and terminations other than
7066045
those on the 600 volt system are to be
7066046
made by PWC Subic. The Contractor is to
7066065
supply splice and terminator kits
complete and any other materials that
are required. The ROICC must coordinate
the work between the Contractor and PWC
so that neither is held up. Be sure that
all materials are on hand to avoid long
outages.
d.
The existing wharf lighting system is
served by Substation No. 5. Keep the
lighting systems operational at all times.
5.
Historical and Archaeological Resources:
01570
When Government monitoring of sensitive
areas is required, the ROICC shall contact
PACNAVFACENGCOM Environmental Planning
Division (Code 23). Usually required where
Native American Indian, Hawaiian, and
Chamorro remains are likely to be
encountered. Submit a work schedule for
approval for these areas. Coordinate with
the Contracting Officer 48 hours prior to
2
|
||