appropriate for the item being reviewed. All copies of the submittal shall be marked
identically. Extensive comments should be forwarded by a separate letter. The A-E may
assume that recommendations are approved unless advised to the contrary. The A-E shall
provide the stamp at A-E's own expense.
COMMANDING OFFICER
[ADDRESS of Contracting Officer]
RECOMMEND:
APPROVAL
APPROVAL SUBJECT TO THE CORRECTIONS NOTED
RETURN FOR CORRECTIONS NOTED AND RESUBMISSION
DISAPPROVAL
Subject to the requirements of:
Contract No. NXXXXX- -C-
Spec. No.
Checked by:  (Signature)
Date
(A-E Firm Name)
4.2.2 Responsibility
To Review Designs performed by others. The A-E is responsible for reviewing all designs
for conformance to site specific requirements, such as pre-engineered metal buildings,
executed by others as part of the construction contract. Shop Drawings and
accompanying designs shall be reviewed and recommended for approval or
disapproval by the A-E. The A-E will stamp and sign these drawings in accordance with
Chapter 7 requirements.
4.3 OPERATION AND MAINTENANCE SUPPORT INFORMATION (OMSI)
REQUIREMENTS
4.3.1 OMSI Manuals
The following types of manuals, with some typical information required, are included in
OMSI packages shown in Attachment E:
a. User Manual: Construction contractor submittals such as Catalog Data,
Operation and Maintenance Data, Test Reports, Shop Drawings, and data
prepared, assembled and indexed in a comprehensive manual. It should also
45