CHAPTER 5. SUBMITTALS
5.1 SUBMITTAL REQUIREMENTS
Submit the types and quantities of documents by project design stages as required by the
Statement of A-E Services. All submittals will be forwarded with project correspondence
referencing project title, project number, location, and A-E contract number. A copy of the
correspondence shall be forwarded to the Contract Specialist.
5.1.1 1391+ and (PCE) Parametric Cost and Estimating
Submit the DD1391+ and PCE documents as required by the Statement of A-E Services
in the CE\VEIQ A-E contract for the cost engineering cost certification method one or two
which ever one is applicable. All submittals will be forwarded with project correspondence
referencing project title, project number, location, and A-E contract number. A copy of the
correspondence shall be forwarded to the Southwest Division Senior Cost Engineer or his
representative. (Distribution identified as (a), (b), (c) and (d), below, are described at the
end of Paragraph 5.1.5a, b, c and d, below.)
5.1.2 15 Percent Design - Distribution (a)
Survey Drawings
Survey Field Notes
Soils Report
Schematic
Engineering Documentation
Energy Conservation Report
Corrosive Soils Report
Asbestos Survey
Geochemical Evaluation
Solar Energy Study
Basis of Design Report - (Mandatory for all projects)
Cost Estimates on Disk
Design Calculations
5.1.3 45 Percent Design - Distribution (a), (c), (d)
Resolution of 15% Review Comments
Environmental Permit Requirements
Short Circuit & Coordination Study
Design Calculations
Basis of Design Report (Revised) - (Mandatory for all projects)
Drawings
Outline Specifications
50








Western Governors University
 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business