CHAPTER 7. DRAWINGS
7.1 GENERAL
MIL-HDBK-1006/1A Drawing And Specifications, as modified by this section, provides
information and requirements for the preparation of drawings. In case of a conflict, the A-E
Guide will govern. Drawings shall include details that are listed in the Naval Facilities
Guide Specifications.
7.1.1 Additive Designation
Portions of work which are to be an Additive Bid Item shall be identified on the drawings as
"Additive Bid Item". Do not include the Additive Bid Item number on the drawings.
Rearrangement of priorities at the last minute or by amendment will be simplified if it is not
necessary to change the drawings.
7.2 DRAWING REQUIREMENTS
7.2.1 Order Of Drawings
Arrange drawings in the following order:
Type of Drawing
Symbol
Title Sheet
T
Civil
C
Geotechnical
GT
Landscape and Irrigation
L
Architectural
A
Structural
S
Mechanical
M
Plumbing
P
Electrical
E
Fire Protection
FP
Cathodic Protection
CP
7.2.2 Title Sheet
The title sheet shall include the vicinity map, location map, location plan, index to drawings,
and a fallout shelter statement, if applicable. The project site, main station entrance, truck
delivery entrance and routes, borrow pits, temporary offices as well as contractor site
storage yards (all dimensioned to indicate spaces set aside) shall be shown on the
location plan. The index shall list drawing reference numbers, drawing titles, and NAVFAC
drawing numbers included in the contract in sequential order and by disciplines.