Share on Google+Share on FacebookShare on LinkedInShare on TwitterShare on DiggShare on Stumble Upon
Custom Search
 
  
 


e. Are instructions on how to breakdown costs required? Yes ___ No ___
f. Will there be specific or special format for submissions? Yes ___ No ___
If yes to any item above, attach description.
II
INFORMATION FOR EVALUATION SECTION 00202
1. "Source Selection." If this project is an RFP and is using evaluation of bids for
selection, complete this section.
"EVALUATION FACTORS FOR AWARD."___________________________________
_____________________________________________________________________
_____________________________________________________________________
______________________________________________
III INFORMATION FOR SECTION 00452
1. Reference FAR 52.223-4, Recovered Material Certification
Does this contract specify the use Recovered Materials? (i.e. materials that have been
collected or recovered from solid waste per FAR 23.402)
Yes_________ No__________
If yes, describe_____________________________________________________
__________________________________________________________________
__________________________________________________________________
IV
INFORMATION FOR SECTION 00102
1. A-E edits entire section "List of Drawings" in SPECSINTACT and submits it complete
at the 100% and final submittal.
Section 00102 included:
Yes______
No_______
V INFORMATION FOR SECTION 00710 OR 00720
1. Reference DFARS 252.210-7000, Brand Name or Equal
Does the project include any Brand Name or Equal statements? Yes____ No____
EXHIBIT 8-B
159








Western Governors University
 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business