EXHIBIT 8-D
PREPARATION OF CHANGE ORDER REQUESTS (COR's)
1. GENERAL: Change Order Requests are identified alphabetically with the order
assigned sequentially in the field by the ROICC. Additions, changes and deletions that are
incorporated into Change Order Requests shall appear in the same order as their original
position in the project manual and drawings. Change Order Requests must include all
previous changes made by amendment.
2. PAGE FORMAT: Unlike amendments, the Change Order Request (COR) requires a
cover sheet provided by the A-E. The format shall conform to the following example:
Specification Number
COR "___"
(Upper right corner)
The following changes shall be incorporated into the project documents for this
project:
Prepared by: [A-E initial and date]
________________________________
PROJECT TITLE
P-123
at the
STATION
CITY, STATE
________________________________
In this location provide a brief, self contained description of the Change Order Request
(COR)
Center the following at the bottom of each page:
COR "__"
Pagination
EXHIBIT 8-D