NO.
DURATION
WORK  TOTAL  IN
STEP DESCRIPTION
STEP
TIME
CENTER HOURS CREW
(HOURS)
120
120
Fixtures, outside procurement time
1
56
56
Navy stock, lead-time
2
40
Build partitions
80
2
3
01
114
2
57
New panel, E.M.T., Wiring
4
21
63
2
31.5
Steam pipes (access area)
5
15
29
Paint exterior building
*87
3
6
02
24
Water pipes (access area)
24
1
7
11
228
2
114
Sand floor and lay tile
8
01
3
42.7
Paint ceilings
9
02
*128
63.6
Paint walls
3
10
02
*191
19.5
Install light fixtures
39
2
11
21
5.5
Install radiators
12
15
11
2
5
Install water coolers
5
1
13
11
Clean up
8
8
1
14
32
*This item is the proportion of the "job phase allowed
time" that is prorated to this particular step reflected
in the Job Phase Calculation Sheet.
FIGURE A-3
Initial Step List