Chapter 1 Facilities Management System
Basic Objective
Classification of Activities
Table 1-1 Elements of Control
Facility History Files
Chapter 2 Responsibility
Major Claimant
Public Works Department (PWD)
Public Works Department (PWD) -Cont.
Fiscal Office
Self Help
Chapter 3 Public Works Contracting
Commercial Activities Cost Analysis
Planning Work to be Contracted
Factors Influencing in-Housing Accomplishment
Contract Types
Contracting Responsibilities
Contracting Support
Contract Funding
Summary
Chapter 4 Work Classification
Specific Job Orders
Table 4-1 Job Analysis
Overhead
Transportation Division Work
Requesting Amendments
Chapter 5 Job Order Identification and Coding
Labor Class Code Definitions/Description
Labor Class Code Definitions/Description -Cont.
Indirect Overhead
Master Job Orders for Housing
Figure 5-1 Daily Time and Labor Distribution Card (NAVFAC 7400/1)
Figure 5-2 Work Authorization/Estimate
Figure 5-3 Job Order for Multiple Expenditure Accounts (Housing)
Table 5-2 Identification of Job Orders
Table 5-4 Branch Code Standardization
Subdividing Work Centers
Chapter 6 Work Generation
Non -Inspection Work Generation
Figure 6-1 Work Request (NAVFAC 9-11014/20)
Customer Relations
Repetitive Requirements
Chapter 7 Work Input Control
Relative Urgency for Accomplishment
Funds Availability
Table 7-1 Level of Maintenance Classification Codes (LMC Codes)
Priorities
Planned Release Date
Figure 7-3 Sample Priority Matrix
Annual Maintenance Plan
Work Input Control Charts
Figure 7-4 Job Requirements and Status Chart
Workforce Availabilty Summary and Work Plan Summary
Figure 7-5 Workforce Availability Summary
Shopload Plan
Figure 7-6 Shop Load Plan
Visible Strips Work Input Control
Work Authorization Document Files
Terminating the Job
Chapter 8 Job Order Preparation and Authorization
Estimating
Additional Instructions for Preparing NAVFAC 11014.22A
Estimate Types
Craft Time
Planning and Estimating A Job Based on A Work Request
Figure 8-1 (1 of 6) Job Phase Calculation Sheet (NAVFAC 11014/23)
Figure 8-1 (2 of 6) Job Phase Calculation Sheet (NAVFAC 11014/23)
Figure 8-1 (3 of 6) Job Phase Calculation Sheet (NAVFAC 11014/23)
Figure 8-1 (4 of 6) Job Phase Calculation Sheet (NAVFAC 11014/23)
Figure 8-1 (5 of 6) Job Phase Calculation Sheet (NAVFAC 11014/23)
Figure 8-1 (6 of 6) Job Phase Calculation Sheet (NAVFAC 11014/23)
Responsibilty for Authorization
Figure 8-2 Sketch of Job
Job Material Coordination
Figure 8-3 Material Requirements/Issue Document (NAVFAC 9-11014/8)
Maintenance and Utilities Divisions
Shop-Stores Material
Supply Department
Cost Recording and Reporting
Chapter 9 Shop Scheduling
Master Scheduling
Figure 9-1 Job Schedule
Figure 9-2 Work Center Labor Hour Availability Log
Master Schedule Board
Schedule Deviations
Figure 9-3 Master Schedule Board - Awaiting Material Section
Figure 9-4 Master Schedule Board - Awaiting Scheduling Section
Master Schedule
Figure 9-5 Master Schedule Board
Figure 9-6 Minor Work Control Board or Log
Work Center Schedule Board
Work Center Schedule for Work Ending
Work Center Schedule for Work Ending
Critical Path Scheduling
Critical Path Scheduling -Cont.
Chapter 10 Report Requirements
Reports
Table 10-1 Tabulated Report A, Feeder Report for Labor Control Report
Table 10-2 Tabulated Report B, Completed Job Orders
Labor Performance Indices
Figure 10-1 Report on Variations on Completed Job Orders
Figure 10-2 Labor Control Report (NAVFAC 9-11014/29)
Control Indices
Analysis of Productive Time
Indirect and Overhead Labor hours
Report on Variations on Completed Job Orders
Base Engineering Support Technical System
Chapter 11 Facilities Management Appraisal and Quality Assurance
Quality Assurance for In-House Operations
Table 11-1 (Section 1) Maintenance Management Appraisal Questionnaire
Table 11-1 (Section 1) Maintenance Management Appraisal Questionnaire -Cont.
Table 11-1 (section 2) Work Input Control and Planning and Estimating Functions)
Table 11-1 (section 2) Work Input Control and Planning and Estimating Functions) -Cont.
Table 11-1 (Section 3) Facility Maintenance Resources
Table 11-1 (Section 3) Facility Maintenance Resources -Cont.
Table 11-1 (Section 4) Shop Scheduling and Work Accomplishment Functions
Table 11-1 (Section 4) Shop Scheduling and Work Accomplishment Functions -Cont.
Table 11-1 (section 5) Management Reports Function
Table 11-1 (section 6 ) Miscellaneous
Table 11-1 (section 6 ) Miscellaneous-Cont.
Appendix A The Critical Path Method (CPM)
Appendix A Procedure
Figure A-1 Job Phase Calculation Sheet
Figure A-2 Work Authorization/Estimate
Figure A-3 Initial Step List
Figure A-4 Arrow Diagram
Determination of Critical Path
Figure A-5 Initial Critical Path
Decreasing Job Duration Time
Figure A-6 Final Critical Path
Job Schedule Bar Chart
Figure A-7 Job Schedule Bar Chart
Figure A-8 Final Step List
Shop Scheduling
Figure A-9 Job Schedule
Appendix B Procedure Charts
Procedure Charts
Chart No.1 Processing Work Request
Chart No.1 Processing Work Request -Cont.
Chart No.2 Processing Work Request
Chart No.2 Processing Work Request -Cont.
Chart No.3 Processing Work Request Funds Under Control of PWD
Chart No.3 Processing Work Request Funds Under Control of PWD -Cont.
Chart No. 4 Processing Work Request Funds Under Control of PWD (Part II)
Chart No. 4 Processing Work Request Funds Under Control of PWD (Part II) -Cont.
Chart No. 5 Initial Processing of Specific Job Orders and Minor Work Authorizations
Chart No. 5 Initial Processing of Specific Job Orders and Minor Work Authorizations -Cont.
Chart No.6 Subsequent Processing of Minor Work Authorizations
Chart No.6 Subsequent Processing of Minor Work Authorizations -Cont.
Chart No.7 Subsequent Processing of Specific Job Orders (Scheduling)
Chart No.7 Subsequent Processing of Specific Job Orders (Scheduling) -Cont.
Chart No.7 Subsequent Processing of Specific Job Orders (Scheduling) -Cont.
Chart No.8 Subsequent Processing of Completed Specific Job Orders
Chart No.8 Subsequent Processing of Completed Specific Job Orders -Cont.
Chart No.9 Labor Reporting Procedure
Chart No.9 Labor Reporting Procedure -Cont.
Appendix C Best Maintenance Control Subsystem
Appendix C The Base Engineering Support, Technical (Best) Maintenance Control Subsystem
Work Input Control ( WIC ) Module
Facilities Engineering Job Estimating (FEJE) Module
Facilities Engineering Job Estimating (FEJE) Module -Cont.
Appendix D Guideline to Division of Procurement Responsibilty
Appendix D Guideline to Division of Procurement Responsibility
NAVSUP COGNIZANCE
References
Naval Facilities Engineering Command Publications Transmittal
Public Works departments, Centers and Offices
Material Support
Cost Recording and Reporting
Labor Performance Indices
Figure 10-1 Report on Variations on Completed Job Orders
Report on Variations on Completed Job Orders
Base Engineering Support Technical System (BEST)
References
Blank Page
Blank Page
Facilities Management
Privacy Statement
-
Copyright Information.
-
Contact Us