Share on Google+Share on FacebookShare on LinkedInShare on TwitterShare on DiggShare on Stumble Upon
Custom Search
 
  
 


MIL-HDBK-1013/12
Table E-16
Actions for Example Number 4, Continued
Action
Action
Procedure
Figure
Structure
Number
Number
Number
165
Is the construction retrofit? Yes.
Installation Cost
Figure 40
<1>
166
Consider cost of hardening wall. Wall
Estimate
<2>
hardening is not required.
167
Does the glazing system weigh over 250
<3>
lb? No. See Figure E-29
168
Is frame cast in place? No.
<5>
169
Include cost of preparing wall for
<7>
anchorage: $100.
170
Include cost of aligning and anchoring
<8>
frame: $125.
171
Calculate installation cost: $450.
<9>
172
Do Initial Cost Estimate procedure
Cost Estimate
Figure 34
<5>
173
Enter base unit cost for cross-section:
Initial Cost
Figure 41
<1>
$0.40. See Figure E-30.
Estimate.
174
Calculate cross-section cost: $564.
<2>
175
Enter base unit cost for frame: $29.
<3>
176
Calculate frame cost: $1334.
<4>
177
Sum component costs: $1898.
<5>
178
Sum component and Installation costs:
<6>
$2348.
179
Life cycle cost estimate. 1.9 x $2348 =
<7>
$4461.
180
Repeat actions 136 through 179 for remaining cross-sections on cross-section selection
worksheet. See Figure E-31 and Figure E-32.
275








Western Governors University
 


Privacy Statement - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business