I.1
Elements of the "Parametric Cost Estimate"
The following is a list of requirements which comprise the PCE.
Revised DD-1391 including updated cost estimates & paragraphs in the "DD 1391 Plus" (forms to be
I.1.1
provided by the AIC/EIC in software format)
Budget Estimate Summary including:
I.1.2
A.
Parametric estimate for basic facility (GUC multipled by the Scope) for normal facilities.
B.
Detailed cost estimate for non-standard features (Special Foundations, Seismic, Environmental
Cleanup. Improvements to existing Utilities Systems. Improvements to existing Road Systems,
Security Lighting, Security Fencing. TEMPEST/HEMP/EMP Shielding, UPS, Built-in Retrieval
Systems. Communications System-OMSI. Site Improvements, Demolition, Dredging, Land
Acquisition, and other major cost drivers)
Detailed Site Investigation Reports addressing:
I.1.3
A.
Soil Borings & Foundation Studies
B.
Environmental Contamination Studies
C.
Utilities Studies for Existing Capacities & Upgrade Requirements
1. Electrical Power
2. Telephone
3. Potable Water
4. Sanitary Sewer
5. Storm Drainage
6. Steam
7. Others
Economic Analysis addressing: (to be provided by the Activity and validated by the A/E)
I.1.4
A.
the alternatives to construction (lease, renovation, addition, alteration, use of other existing
facilities, etc.)
B.
life cycle cost for each alternative