Custom Search
 
  
 


C.
the rationale for selecting new construction as the best alternative to satisfy the requirement.
NEPA Documentation (to be provided by Code 20):
I.1.5
A.
For Category Exclusion (Cat Ex): Signed Categorical Exclusion Form.
B.
For Environmental Assessment (EA): All EAs will be underway. Provide anticipated Finding of
No Significant Impact (FONSI) date. Provide a discussion of the environmental alternatives
considered and why the subject project was selected as the solution. Discuss and environmental
impact and associated mitigation costs.
C.
For Environmental Impact Statement (EIS): Documentation should be well underway, nearing
Draft EIS. Provide anticipated schedule for completion. Provide a discussion of the
environmental alternatives considered and why the subject project was selected as the solution.
Discuss any environmental impacts and associated mitigation costs.
Site Approval should be complete [to be provided by the Activity; conditional approval for those
I.1.6
requiring Department of Explosive Safety Boards (DDESB) Final Safety Review].
Complete Facility Schematics only for Highly Complex Facilities such as Chemical Processing Plants,
I.1.7
Industrial Waste Treatment Plants, Dry-docks, Hospitals, Biological Research Facilities, Nuclear
Weapons Support Facilities, etc.
Estimated Design Milestones (A/E to input data provided by the AIC/EIC onto software forms.)
I.1.8
I.2
Elements of the "DD 1391 Plus"
Discussion of the five elements: Requirement, Scope, Cost, Alternatives, and Doability are to be included in the
various blocks of the DD 1391. (An example is included.)
Block 1.
Component (of DOD)
Block 2.
Date
Block 3.
Installation & Location/UIC
Block 4.
Project Title
Block 5.
Program Element (Left blank)
Block 6.
Category Code
Block 7.
Project Number
Block 8.
Project Cost (S000) (based on GUC)
Block 9.
Item Cost Estimates