Specifications:  Complete with cover sheet; and hard copies printed
from PDF (Portable Document Format) files.  SPECSINTACT files
converted to PDF with bookmarks and visual thumbnails.
Project Information Form (completed by A-E and PDE)
Basis of Design (if not revised from the 60% stage, state on
cover sheet)
Design Calculation (if not revised from the 60% stage, state on
cover sheet)
Cost Estimates
Collateral Equipment List (if not revised from the 60% stage, state
on cover sheet)
Furniture Layout
OMSI Outline  (Refer to NFGS-01781 and CCB (OMSI SOW))
List of Submittals Required in Project Specifications (Appendix J)
List of Submittals Required for PCAS (Appendix J)
Critical Items Summary
Recommendations on Field Consultations
Construction Schedule (Simplified Critical Path Method, Bar Graph,
or other required method)
Soil Investigation Report (if not revised from the 60% stage,
state so on the cover sheet)
Review comments and marked review copies of the 60% submittal
Design Review Checklist and Redicheck Coordination Review Checklist
(Appendix I)
Bid Items
Preliminary Hazard Analysis Worksheets (Design A-E comments in
The "status" column) (See PACDIV CAP408)
DQCP Requirements (paragraph 3.2.1; including but not limited to
Quality Check-Set and Checklists)
3.1.7  100% Review Conference:  Copies of the A-E list of issues and the
review comments with the A-E's annotations will be made available to
anticipated attendees.
3.1.8  Final Submittal:
Include the originals as applicable to the
project:
Drawings:  Phase 1) Originals signed by A-E; and hard copies.  Phase
2) After originals approved by PACNAVFACENGCOM and returned to A-E
(submittal to PACNAVFACENGCOM within one week maximum):  CADD files on
CD-ROM; originals scanned to PDF and produced as an EBS (Electronic
Bid Solicitation) document on EBS CD-ROM; and hard copies printed from
the EBS CD-ROM.  Originals signed by A-E and PACNAVFACENGCOM.
Specifications:  Phase 1) Originals signed by A-E; SPECSINTACT files
converted to PDF with bookmarks and thumbnails; and hard copies
printed from PDF.  Phase 2) After originals approved by
PACNAVFACENGCOM and returned to A-E (submittal to PACNAVFACENGCOM
within one week maximum): SPECSINTACT files on CADD CD-ROM;
SPECSINTACT files converted to PDF with book marks and visual
thumbnails on EBS CD-ROM; and hard copies printed from the EBS CD-
ROM. Also one diskette with Submittal Register (Refer to SPECSINTACT
"User Guide"; click on "Submittal Formatting Requirements," select
"Submittal Register Program").  Originals signed by A-E and
PACNAVFACENGCOM.
3-3