8.13 SUBMITTALS AND TESTING LIST
Generate the Submittal List, Submittal Register, and Test Report from SPECSINTACT.
Identify submittals to be approved by the GOVERNMENT with a "G."
8.14 SUBMITTALS
Prior to printing, the A-E should use the SPECSINTACT error reports for checking and
correction errors.
8.14.1 45 Percent Submittals
The 45 percent submittal shall include an Outline Specification in the format of Exhibit 8-F.
Outline Specifications may be required for large, complex projects such as hospitals prior
to 45 percent. Verify with the PL for the specific project.
8.14.2 Basis Of Design
Submit in accordance with Chapter 6, Basis Of Design.
8.14.3 100 Percent Submittal
Specifications shall be complete, camera ready, with all elements thoroughly checked and
coordinated with the drawings, and with sufficient detailed information to permit accurate
bidding and construction of the project. If the project is to be "fast-tracked", where the 100
percent submittal is to be used for advertisement, and bids conform to final submittal
requirements, provide the following:
a. Specifications on magnetic media consisting of backup of the edited job "Pull
Files" on disks using the SPECSINTACT system.
b. Bound hard copies of the specifications. Include cover sheet and required blank
forms (NFGS 01330 and 01450). The separately generated project cover sheet on
CCB may be included.
c. Copy of the Submittal Register and Test Reports.
d. Copy of the Project Information Form.
8.14.4 Final Submittal
Specifications shall be complete, camera ready, with all elements thoroughly checked and
coordinated with the drawings, and with sufficient detailed information to permit accurate
bidding and construction of the project. Provide the following: